5 phases, 16 tasks
Demo → framing → rough-in → inspection → finish → handover, plus a 2-day buffer before the client walkthrough.
A ready-to-use schedule for small remodel, installation, and HVAC crews. Five phases, sixteen tasks, owners, durations, and dependencies — the structure that keeps a 30-day job from slipping into week seven.
No email required · Excel or ScheBot · 5 phases / 16 tasks
Most schedule templates are a list of tasks. This one keeps the two columns that prevent rework: who owns it, and what must finish first.
Demo → framing → rough-in → inspection → finish → handover, plus a 2-day buffer before the client walkthrough.
“Crew A”, “Crew C”, “Inspector”, “PM” — so the schedule answers “who is doing what next week” without a phone call.
Inspection depends on electrical, plumbing, and HVAC. Change one date and you can see what moves with it.
Open it in Excel or Google Sheets. The first ten rows:
| Phase | Task | Owner | Start day | Duration | Depends on |
|---|---|---|---|---|---|
| Demo | Protect floors and disconnect utilities | Crew A | 1 | 1 | — |
| Demo | Remove cabinets and fixtures | Crew A | 2 | 1 | Demo - Protect floors |
| Framing | Layout and framing changes | Crew B | 3 | 2 | Demo - Remove cabinets |
| Electrical | Rough-in electrical | Crew C | 5 | 2 | Framing |
| Plumbing | Rough-in plumbing | Crew C | 5 | 2 | Framing |
| HVAC | Duct and vent adjustments | Crew C | 6 | 2 | Framing |
| Inspection | Rough-in inspection | Inspector | 8 | 1 | Electrical; Plumbing; HVAC |
| Insulation | Insulation and drywall | Crew B | 9 | 3 | Inspection |
| Drywall | Drywall finish and sanding | Crew B | 12 | 3 | Insulation |
| Paint | Prime and paint | Crew D | 15 | 3 | Drywall |
The CSV includes all 16 tasks plus the buffer. Download it here.
Excel → Data → From Text/CSV, or double-click the file. Keep “Start day” and “Duration” as numbers.
Set the project start date, then calculate each task date as start + day. Add conditional formatting for overdue rows.
When a date moves, the dependency column tells you what else has to move. Delete it and the schedule becomes a wish list.
Load the template once, then update it from site. ScheBot flags double-booked crews and broken dependencies before you publish.
Name it, set the 30-day window, invite the crew.
Each CSV row becomes a task: phase, owner, start day, duration, dependency.
ScheBot checks leave, non-working days, and crew overload before the plan goes out.
Yes. Download the CSV without an email address. Use it in Excel, Google Sheets, or load it into ScheBot.
Yes. Rename phases and tasks, change durations, and keep the dependency column. The structure works for remodel, installation, HVAC, electrical, and event production schedules.
Create a project in ScheBot, then map each row to a task: phase, owner, start day, duration, and dependency. Book a 20-minute demo and we will load it with you.